The Millennial

Bhatara, Dhaka

Expected Completion DateAugust 2026
Status UpdatedJuly 2026
← Back to all projects
The Millennial

Construction progress details

The progress table comes directly from the latest site update.

SL. NoName of the workProgress details
1Foundation work100% completed
2Basement work100% completed
3Super Structure work100% completed (Tower-1, Tower-2, Tower-3)
4Block WorkTower-01: all 8 apartments (A1 to A8) 100% completed. Tower-02: all 55 apartments 100% completed. Tower-03: all 51 apartments 100% completed.
5Electrical conduiting workOverall apartments 100% completed. Common area 90% completed.
6Door frame fitting workOverall 100% completed
7Sanitary & plumbing line workInternal wiring 100% completed
8Inside plastering workOverall 100%
9Electrical cable wiring work100% apartments completed
10Wall tiles workTower-1: 100%, Tower-2: 100%, Tower-3: 98% complete
11Common sanitary & plumbing line workOverall 95% completed
12Outside plastering workTower-1 completed. Tower-2: 100%, Tower-3: 100%
13Floor tiles/Marble workTower-1: 100% completed, Tower-2: 100% completed, Tower-3: 95% completed
14L.C.C workTower-1 completed, Tower-2: 100% completed, Tower-3: 100% completed
15Grill & Railing workTower-1: 100% completed, Tower-2: 100% completed, Tower-3: 100% completed
16Inside paint & polishing workTower-1: 1st and 2nd coat 100% complete. Tower-2: 1st coat 100% completed. Tower-3: 1st coat, 10 apartments completed.
17Switch-Socket fitting workTower-1 completed. Tower-2: 100% completed.
18Outside paint workTower-1: 1st coat completed. Tower-2: 100% completed.
19Door shutter workTower-1 completed. Tower-2 completed.
20Aluminum workTower-1: 100% completed, Tower-2: 100% completed, Tower-3: 90% completed
21Tiles pointing & marble finishing workTower-1 wall: 100% completed. Tower-2: 95% completed.
22Commode-Basin fitting & C.P fittings work100%
23Lift/Generator/Substation/Solar work95%
24Boundary wall/Ground floor development work95% completed (boundary wall 95%, plaster 95%)
25Roof top finishing workTower-1 tile work: 100% completed. Tower-2: 95% completed. Tower-3: 95% completed.
26Roof top gardening / G.F garden workNot yet started
27Landscape / logo work90%